|
With
the heavy thuds of its huge twin rotors and a deafening roar of
its engines, the powerful Chinook military helicopter destroyed
the peacefulness of the English county of Cumberland.
The
helicopter steered its way precisely towards its target as the load
it carried slowly approached its final destination. This was no
mountain rescue on Scafell or at Helvellyns Striding Edge.
Under the powerful flying equipment were prefabricated bridge supporting
girders supplied by ASD Glen Metals. These supporting girders represent
the backbone of a new pedestrian bridge in a historical and architecturally
sensitive area. And without the major part played by the Chinook
helicopters, the unusual design of the bridge would not have been
possible. The interesting pedestrian bridge is situated approximately
150 meters from the remains of a Roman river crossing. It puts the
finishing touch to one of the most important links in the National
Trail Project. This project plans for a continuous footpath to be
completed in June 2001. It leads from the remains of Hadrians
Wall between Wallsend not far from Newcastle-upon-Tyne in
the East and Bowness-on-Solway at the Solway Firth in the
West.
Various
questions and problems arose for the architects and engineers when
designing this bridge, because it was necessary to consider how
the new structure would fit into a landscape constantly shaped by
history. Not only that but three entirely different interests had
to be reconciled: 1. preservation of the nearby architectonic sights
2. requirements of the surrounding agricultural areas and 3. problem-free
access for pedestrians. There was also a need to consider how the
time required for construction in situ could be reduced. A solution
had to be found for the extremely difficult task of dispensing with
the use of heavy duty transport machinery and cranes. And, finally,
how far would it be possible to reduce the need for future maintenance
measures. At the design phase, the team decided against solutions
requiring the use of masts or other very large elements. After all,
tampering with the environment was to be minimised. Instead they
chose a design that kept the number of fixtures in the ground to
a minimum, thereby limiting both the architectonic and ecological
effects of the bridge construction. The designers then had to consider
how to deal with the difference in height of 4.60 meters between
both banks. It was decided that it would be reasonable for the users
of the bridge if shallow steps were incorporated to compensate for
the height difference during crossing, especially as it had already
been agreed that the bridge was being designed primarily for pedestrians.
For
this reason, the resulting structure consists of two slightly inclined,
prefabricated steel beams supported at their lower ends on a concrete
pad, and on the opposite bank by a pair of cantilevered steel columns,
which also sit on concrete pad foundations. The two beams are connected
by a deep, shaped cross beam on top of the columns. The main span
over the river is 31.7 meters but the bridge itself cantilevers
another 7.5 meters beyond the column supports to reach the embankment.
This allows the depth of the beams to vary between 325 mm and 1,100,
and to allow as light a touch as possible with the ground at the
top end because of unsuitable ground conditions at the upper end
of the bridge.
It
took 25 tonnes of Corten steel in panels with a size of 3 x 2 to
8 x 2 meters with thicknesses of 6, 10 and 25 mm supplied
from the warehouse of ASD Glen Metals to build the bridge.
Starting from flat plate all bridge components were manufactured
by Hartlepool Steel Fabrications under the supervision of Contract
Manager Mike Wood. Corten was selected as the best bridge material
because it contains copper. Copper forms a patina that gives the
material lasting protection against rust; after all, maintenance
was to be kept to a minimum. And it leaves behind a red brown colour
that blends in with the area surrounding the bridge. The prefabricated
deck of the bridge is made up of wooden planks of a length of 2.50
meters and a width of 75 mm that can be removed for maintenance.
The oak handrails are supported by flat plates on top of stanchions
that are inclined in such a way that they appear to point down the
slope of the bridge. The stanchions and the handrail support are
also made of Corten steel.
The
duration of the contract was fixed at just 8 weeks. To prevent the
need for heavy goods vehicle access, the bridge beams were delivered
in two parts by helicopter. The cement was delivered in baskets
by tractor. It is a very attractive bridge, says Mike
Wood. Even if it was quite a simple project from the point
of view of production, it was all the more difficult, given the
short duration of the contract, to obtain the right quantities of
Corten steel in time. And this was where the team at ASD Glen Metals
did not let us down. The MOD was involved in the project right from
the tender phase. If they had not been able to provide the Chinook
helicopter, the bridge would never have been built. The pedestrian
bridge over the Irthing was commissioned by the Landscape Commission
and Cumberland County Council and designed by the Napper partnership
of architects in co-operation with the consulting engineers Ove
Arup and Partners. John Laing was the building company supervising
operation . Hartlepool Steel Fabrications realised the individual
components of the bridge.
|